DHAKA, Nov 17, 2026 (BSS)- The government has taken a Taka 2,769.86 crore project to procure 30 new meter-gauge diesel-electric locomotives for Bangladesh Railway, aiming to ease an acute shortage of engines, replace ageing ones and increase the railway’s capacity to transport passengers and goods.

The ‘Expansion of Railway Capacity’ project is expected to strengthen train operations across key meter-gauge routes, creating greater opportunities for freight services alongside passenger trains.

Of the total project cost, the government will provide Taka 811.38 crore, while the remaining Taka 1,958.48 crore will come as a loan from the Asian Infrastructure Investment Bank (AIIB), accounting for around 71 percent of the financing.

The Executive Committee of the National Economic Council (ECNEC) approved the project at a meeting chaired by Prime Minister Tarique Rahman on October 7. It is scheduled to run from July 1, 2026, to December 31, 2029.

Talking to BSS, Bangladesh Railway Director General Md Afzal Hossain said the shortage of locomotives was one of the biggest obstacles to expanding freight transportation.

“Many of our trains are still being operated with old locomotives. The addition of 30 new meter-gauge locomotives will significantly ease the shortage and improve our capacity to provide passenger and freight services,” he said.

According to Bangladesh Railway data, the organisation currently has 292 locomotives, including 164 meter-gauge and 128 broad-gauge engines.

However, 115 of its meter-gauge locomotives have already exceeded their economic lifespan of 20 years. Of those, 62 are more than 40 years old.

Prolonged use has reduced their operational efficiency, while sourcing spare parts for the ageing engines has become increasingly difficult and expensive, BR officials said.

Breakdowns often require lengthy repairs, disrupting train schedules and limiting transportation capacity.

Each new locomotive under the project is estimated to cost around Taka 69 crore. The supplier country or company has not yet been selected. Suppliers will be chosen through an open international tender.

Besides purchasing the locomotives, the project includes procurement of spare parts, maintenance equipment, specialised tools and technical assistance.

Training will also be provided to railway engineers, supervisors and other employees involved in locomotive operation and maintenance.

Railway Secretary Md Fahimul Islam said the government wants to develop the railway not merely as a passenger transportation service but also as a major contributor to the country’s freight movement and economic activities.

“Expanding railway capacity is essential to reduce pressure on roads and establish a comparatively cost-effective transportation system. Procuring new locomotives is an important part of that plan,” he said.

Currently, only around 3-4 percent of Bangladesh’s domestic freight is transported by rail, despite its potential to carry large volumes of goods over long distances at relatively low costs.

Railway freight volumes have also declined in recent years. The railway transported 54.67 lakh tonnes of goods in fiscal 2020-21, 53.33 lakh tonnes in 2021-22 and 44.14 lakh tonnes in 2022-23.

Major commodities transported by rail include rice, wheat, fertiliser, petroleum products, stones, sand, industrial raw materials and containers.

Railways also have significant potential to transport imported goods from Chattogram Port to different parts of the country.

However, shortages of locomotives and wagons, inadequate freight train services and weaknesses in cargo loading and unloading facilities have prevented the railway from fully exploiting this potential.

The BR officials said the organisation needs approximately 70-80 additional locomotives, indicating that the procurement of 30 engines will address only part of the existing shortage.

State Minister for Railways Habibur Rashid said the government was taking a phased approach to procuring new locomotives to address the shortage, particularly on meter-gauge routes.

He said the project would reduce dependence on outdated engines, improve passenger and freight transportation and facilitate the development of a modern, technology-based railway system.

The government is also planning to expand freight services along major commercial corridors, including Dhaka-Chattogram, by making better use of double-track railway sections.

Other initiatives include procuring additional wagons, expanding regional and sub-regional rail connections and developing inland container depots (ICDs) and logistics hubs.

According to the BR’s master plan, the government aims to convert meter-gauge lines into dual-gauge tracks by 2040.

However, the transition may take considerable time, and meter-gauge trains could continue operating on some routes until 2055-60.

Against this backdrop, officials consider the procurement of new meter-gauge locomotives essential to maintaining the existing network until the conversion is completed.

The new engines are expected to benefit important railway areas across the country covering Dhaka, Narayanganj, Gazipur, Mymensingh, Sylhet, Chattogram, Cumilla, Noakhali, Brahmanbaria and Cox’s Bazar.

The officials said alongside infrastructure development and increased wagon availability, the new locomotives will help strengthen the railway’s role in passenger and freight transportation, reduce pressure on roads and support the country’s economic activities.